Who to Hire at Each Stage of a Data Center Build

Nov 18, 2026

A data center build needs different people at each stage, and the hardest roles take the longest to fill. Preconstruction calls for estimators and a project executive, the structure phase for superintendents, the equipment phase for electrical and mechanical leads, and the final months for commissioning and operations staff. Start recruiting each group well before its stage begins.

  • Hire the project executive and preconstruction team before the design is finished.
  • Bring the general superintendent on before site work starts, not after.
  • Electrical and mechanical superintendents need to be in place before equipment arrives.
  • Commissioning managers should join early enough to witness factory testing.
  • Operations staff should overlap with commissioning so knowledge is not lost at handover.

Why timing matters on a data center build

Timing matters because every stage of a data center build depends on the one before it, and tenants plan around a fixed handover date. A superintendent who arrives a month late inherits problems they did not create. A commissioning manager who joins after factory testing misses the first chance to catch faults. Late hires cost more than early ones.

The scale of current programs makes this worse. JLL counted more than 66 GW of capacity under construction across North America at midyear 2026, and much of it competes for the same experienced people. Contractors who wait until a stage begins often find the best candidates already committed elsewhere.

How far ahead should contractors start recruiting?

Contractors should start recruiting senior roles several months before they are needed, and longer for the scarcest positions. Commissioning managers, electrical superintendents and project executives with hyperscale experience are rarely available at short notice. Building the hiring plan alongside the construction schedule is the simplest way to avoid gaps.

Stage 1 covers preconstruction

Preconstruction is where the contractor prices the job, plans the schedule and works with the design team. The key hires are a project executive to own the client relationship, a preconstruction manager to lead the bid and estimators to price electrical, mechanical and civil scopes. Decisions made here shape the whole project.

Electrical estimators are especially important, because power equipment makes up a large share of cost and has long lead times. Our preconstruction manager hiring page explains what to screen for.

Who owns the project during preconstruction?

The project executive usually owns the project during preconstruction, supported by the preconstruction manager. Together they set the budget, agree the schedule with the owner and plan procurement for long lead equipment such as switchgear and generators. Bringing the future project manager into these conversations early helps the handoff into construction.

Stage 2 covers site work and structure

Site work and structure cover grading, utilities, foundations and the building shell. The general superintendent leads the site and needs to be in place before the first crews arrive. Project managers coordinate subcontractors and track cost. A QA and QC lead should start now, because the evidence trail for later testing begins with the first pour.

Is this the easiest stage to staff?

It is usually the easiest, because the skills overlap most with general commercial construction. Experienced site superintendents and civil managers can move across from other large projects. The risk is hiring for this stage alone and then discovering the same people lack the electrical depth the next stage demands.

Stage 3 covers equipment and MEP installation

Equipment and MEP installation is the longest and most labor-intensive stage. Switchgear, transformers, UPS systems, generators, chillers and air handlers arrive and are set, then connected by miles of cable and pipe. Electrical and mechanical superintendents, foremen and MEP project managers carry this stage, and their experience decides how smoothly it runs.

This is where most contractors feel the talent shortage most sharply. Our electrical superintendent and mechanical superintendent hiring pages cover both roles.

Which roles should be hired first in this stage?

Electrical superintendents should be hired first, because power equipment arrives early and sets the critical path. Mechanical superintendents follow closely, especially on buildings with liquid cooling. Foremen can often be recruited closer to need, but the leads who plan the work and manage vendors must be in place before deliveries begin.

Stage 4 covers energization

Energization is the moment the building receives permanent power and systems come alive for the first time. It is a high risk point, so contractors rely on experienced electrical leadership, critical power specialists and vendor field service engineers who start up UPS systems, switchgear and generators. Safety and sequencing discipline matter more here than anywhere else.

Critical power specialists are often the hardest people to find at this point. See our critical power specialist hiring page.

What goes wrong at energization?

Most problems at energization come from sequencing errors, incomplete terminations or protection settings that do not match the design. An experienced electrical lead catches these through careful lockout, testing and step by step switching plans. Contractors who staff this stage with first-timers often lose days to faults that a seasoned team would have prevented.

Stage 5 covers commissioning

Commissioning proves that every system works alone and together. It runs in five levels, from factory testing through integrated systems testing, where the team deliberately cuts utility power to prove the building recovers. The commissioning manager leads, supported by electrical and mechanical commissioning engineers who write and run the test scripts.

Commissioning managers should join early enough to witness factory testing, even though the heaviest work comes at the end. Oracle reported 618 MW delivered across 6 of 8 Abilene campus buildings by September 2026, and every one of those buildings needed a full commissioning program.

Why hire commissioning staff so early?

Hiring commissioning staff early lets them catch faults at the factory and during installation, when fixes are cheap. A commissioning manager who arrives only for the final tests has no history with the building and must learn everything at once. Early involvement also helps them write scripts that match how the systems were actually installed.

Stage 6 covers handover and operations

Handover moves the building from the contractor to the owner’s operations team. Critical facilities managers, data center operations managers and shift engineers take responsibility for keeping it running. The best handovers overlap these hires with commissioning, so the people who will run the building watch it being tested and learn its quirks first hand.

Our critical facilities manager hiring page covers the lead operations role.

How to plan hiring across a data center build

Planning hiring across a data center build takes five steps, and the work starts before ground is broken. Preston Recruitment helps contractors map each senior hire against the program so no stage starts without its leaders. Follow these steps to keep recruiting ahead of the schedule rather than chasing it.

  1. Step 1 List every senior role the program needs, stage by stage.
  2. Step 2 Mark the date each role must be on site.
  3. Step 3 Work back from that date to set a recruiting start date.
  4. Step 4 Start the scarcest roles first, including commissioning and electrical leads.
  5. Step 5 Review the plan monthly as the schedule moves.

Frequently asked questions

What are the stages of a data center build?

A typical data center project moves through preconstruction, site work and structure, equipment and MEP installation, energization, commissioning, and handover to operations. Some stages overlap, especially installation and early commissioning. Each stage needs different specialist hires, and the most technical stages come toward the end of the program.

Who should be hired first on a data center project?

The project executive and preconstruction team should be hired first, because they shape the budget, schedule and procurement plan. The general superintendent follows before site work begins. Electrical leadership and the commissioning manager should be secured well before equipment arrives, because both are scarce.

When should a commissioning manager join?

A commissioning manager should join early enough to witness factory acceptance testing, which often happens months before equipment reaches site. Early involvement lets them catch faults when fixes are cheap and write test scripts that match the installed systems. Joining only for final testing leaves them at a disadvantage.

Which data center roles are hardest to fill?

Commissioning managers with integrated systems testing experience, electrical superintendents who have energized large buildings and critical power specialists are among the hardest roles to fill. Project executives with hyperscale experience are also scarce. Starting these searches early is the most reliable way to secure the right people.

Should operations staff overlap with construction?

Yes. Operations staff who overlap with commissioning learn how the building behaves under test and inherit knowledge that is otherwise lost at handover. Critical facilities managers and shift engineers who watch integrated systems testing take over a building they already understand, which reduces risk in the first months of operation.

Planning hires for a new program? Send us your brief.

About the Author

James Preston is the founder, CEO and managing director of Preston Recruitment, which he started in 2019. He leads the firm’s US direct-hire practice, recruiting general managers, project executives, project managers, superintendents, estimators and commissioning leaders for data center, mission critical, electrical and mechanical contractors.